Proposed Projects

Please check here for the latest information on proposed improvements to our water system!

  • Water System Improvements & Repairs Project
    July 31, 2026

                                                           CLAY-ROANE PUBLIC SERVICE DISTRICT

    CLAY AND ROANE COUNTIES, WEST VIRGINIA

    WATER SYSTEM MPROVEMENTS & REPAIRS - PHASE 1

    BACKGROUND

    The Clay-Roane Public Service District currently serves 930 customers with potable water in southern Roane County and western Clay County. The PSD, which began operation in 1982, has 70 miles of water mains, seven tanks, five booster pumping stations and an 87-gpm water treatment plant. Over the past ten years, the PSI) has experienced over 125 main line leaks in the Amma and Pigeon areas, and those leaks have resulted in frequent and prolonged water outages for many customers. In addition to replacing the water mains in the Amma and Pigeon areas, failing equipment in the booster pumping station and Pressure Reducing Stations needs to be replaced to reduce the number of leaks and the number and duration of water outages; replacing the existing manual-read and touch-read water meters will improve efficiencies and allow more maintenance time to be devoted to finding and repairing leaks.

    The Clay-Roane PSD has worked diligently to repair and replace failing pipe and equipment, but with rates currently exceeding $70/month (seventh highest rate in West Virginia), which equates to over 2.4% of MHI, making significant progress with leak reduction has been very difficult.

    PROPOSED PROJECT

    The proposed project will include:

     Replacing 50,000 LF of 2-inch, 6-inch and 8-inch mains

     Replacing (74) 2-inch — 8-inch valves

     Replacing 1, OOO water meters with new touch-read meters

     Refurbish (3) Pressure Reducing Stations

     Refurbish or Replace (3) booster pumping stations.

    In addition to the "Congressionally Directed Spending" (CDS) grant, funding for the project will be obtained from the WV Bureau for Public Health's DWTRF and from the WV Infrastructure & Jobs Development Council.

     

     

     

    CLAY-ROANE PUBLIC SERVICE DISTRICT

    WATER SYSTEM IMPROVEMENTS & REPAIRS - PHASE 1

    PROJECT SCHEDULE

    The project schedule is shown below.

    Professional Services Acquired……………………………………………………... March 30, 2023

    All Agreements Executed & Approved, excluding Construction...............................Ju1y 1, 2023

    Plans & Specs Submitted to Applicable Agencies………………………………………………June 15, 2024

    All Permits Submitted......June 15, 2024

    Final Plans & Specs Approved ......................................................................September 15, 2024

    Rule 42 Completed ..June 15, 2024

    Municipal Rate Ordinance Completed................July 15, 2024

    Request for All Binding Commitments ................. September 15, 2024

    File PSC Certificate Case September 1 5, 2024

    80% ROWS & Easements, and 100% Land Acq. Recorded .......................... September 15, 2024

    Request Authorization to Bid.............................................................................. December 15, 2024

    Advertise for Bids...............................................................................................January 15, 2025

    Bid Opening.................February 15, 2025

    100% ROWs, Easements & Land Acquisitions Recorded February 15, 2025

                       All Permits and Clearances Obtained ……………………..…………………………………..February 15, 2025

    PSC Certificate Final.……….. February 15, 2025

    Award Contracts ..............March 1, 2025

    Start Construction…………………………………………………………………………………….........March 15, 2025

    Project Completion ...........Ju1y 31, 2026